Excerpts from Weekly Report


Friday | Nov. 30, 2001
The Advanced Camera for Surveys (ACS) arrived at KSC.
The Crew Aids and Tools (CATs) were received at KSC.

The SAC and Multi-Use Lightweight Equipment (MULE) post shipment CPTs were successfully completed.

Near Infrared Camera and Multi-Object Spectrometer (NICMOS) Cooling System (NCS)/Aft Shroud Cooling System (ASCS) Integration of the relay box controllers into the Electronic Support Module (ESM) has been completed. Regression testing (vibration and Thermal Vacuum [TV]) was complete.

The sixth HST Crew Fam was successfully completed. All seven crewmembers participated.

Kennedy Space Center
Vehicle: Columbia/OV-102
Shuttle & Payload Processing Status Report


Tuesday | Nov. 20, 2001
Columbia is in the Orbiter Processing Facility (OPF) undergoing pre-launch processing for the Hubble Space Telescope servicing mission. Airlock verification and Auxiliary Power Unit (APU) leak and functional testing are continuing, and preparations are under way to install the Main Engine heat shields.

 

Latest ::
Goto hubble.nasa.gov
Post-Mission ::
Late Apr
Mid Apr
Early Apr
Late Mar
Mission ::
Mar 12
Mar 11
Mar 10
Mar 9
EVA 5 : Mar 8
EVA 4 : Mar 7
EVA 3 : Mar 6
EVA 2 : Mar 5
EVA 1 : Mar 4
Mar 3
Mar 2
Mar 1
Pre-launch ::
Feb Week 4
Feb Week 3
Feb Week 2
Feb Week 1
Preparation ::
Late Jan
Mid Jan
Early Jan
Late Dec
Mid Dec
Early Dec
Late Nov
Mid Nov
Early Nov
Late Oct
Mid Oct
Early Oct
 
 
 
Glossary | FAQ | Links                Talk to Us!
  :::::: Contact: webmaster@sm3b.gsfc.nasa.gov | Global Science & Technology, Inc. ::::::
| Page Last Updated: October 24, 2005 |
Links FAQ Glossary Talk to Us! SiteMap Home